What a piece actually costs.

WHAT TO INCLUDE

Timber and sheet material, at quantity used including waste Veneer and edging Hardware Adhesives and abrasives Finishing materials Labour, by operation Machine time Transport and installation Overheads

WHAT PEOPLE OMIT

Waste Abrasives and consumables Finishing time Delivery and installation Their own time

WHY WASTE MATTERS

Cutting from boards and sheets produces offcuts, and the yield is never complete.

WHAT TO MEASURE

Actual material consumed per piece.

WHY MEASURED

Costing on the theoretical requirement understates cost consistently.

HOW TO COST LABOUR

Time each operation, and apply an hourly rate.

WHAT OPERATIONS TO TIME

Cutting and machining Assembly Sanding and preparation Finishing Fitting hardware Installation

WHY SANDING AND FINISHING SPECIFICALLY

They consume far more time than anyone estimates and they are routinely omitted.

WHAT TO ESTABLISH

Standard times for pieces you make repeatedly.

WHAT THAT ENABLES

Accurate quoting and realistic scheduling.

WHAT TO ADD

An allowance for rework.

WHAT TO CALCULATE

Cost, then the price required for your margin.

WHAT TO DO IF THE PRICE EXCEEDS WHAT CUSTOMERS PAY

Simplify the design, change materials, or improve the method.

WHAT NOT TO DO

Absorb it by underpaying yourself.

WHY

It conceals an unviable product.