Designing for the future.

WHAT CONSTRAINS GROWTH

Power, first Cooling, second Space, last

WHY THAT ORDER SURPRISES PEOPLE

Facilities run out of power and cooling long before they run out of floor space.

WHAT TO PLAN

Power distribution capable of supporting future density Cooling capable of removing the resulting heat Space for additional plant, not only racks

WHAT DENSITY MEANS

Power consumed per rack.

WHAT HAS CHANGED

Equipment has become far denser, and modern workloads more so again.

WHAT THAT MEANS

Facilities designed years ago frequently cannot support modern equipment at full density.

WHAT TO ASK

What power per rack the facility supports.

WHAT TO PLAN FOR

Phased build, so capacity is added as demand appears.

WHY

Building everything at once wastes capital on unused capacity.

WHAT TO AVOID

Filling every rack immediately, leaving no room for growth or maintenance.

WHAT TO MONITOR

Power and cooling utilisation, against capacity.